PHASE TIMELINE *
ACTIVITIES BEGIN 10 TO 14 DAYS AFTER CONTRACTS ARE SUBMITTED AND APPROVED.
WELCOME WEEK 1
  • 30 minute phone call with the Manager of Client Services to establish points of contact, review installation of remote access software, and schedule the next meeting. Online user list (completed within 2 business days by Practice Champion), and online discovery document (completed within 3 business days).

BRIDGE TO SUCCESS WEEK 1
  • 60 minute call with Office Manager, Practice champion and head physician to review the “Bridge to Success” presentation.
TRAINING TRACK WEEK 2
  • 30 minute call with Practice Champion to review online academy
  • Review methods of finding answers; including F1, user manual, and Allscripts Academy.

CONFIGURATION WEEK 3-4
  • Review Hardware install and readiness. Proceed with training after Hardware and software is in place. Practice installs MyWay on all machines.
  • 90 minute call with Practice Champion. Practice starts using MyWay. Training of areas that will need to configure in the database.

OFFICE TRAINING WEEK 4-5
  • Two office training sessions to review front office areas of MyWay through remote sessions. Start to use front office areas in practice
  • Review Allscripts Academy progress and worksheets.
BILLING TRAINING WEEK 6-9
  • Review billing areas of MyWay through remote sessions.
  • Review Allscripts Academy progress and worksheets. Start to bill through MyWay system.

CLINICAL TRAINING WEEK 6
  • Review clinical areas of MyWay through remote sessions.
  • Review Allscripts Academy progress and worksheets. Start using the MyWay clinical system.

READINESS REVIEW WEEK 10
  • Run through of all systems; including practice understanding of MyWay, hardware readiness, and workflows.
END DATE WEEK 11
  • Billing, Front-office, and Clinical portions of MyWay working
POST-LIVE SUPPORT WEEK 12-15
  • Questions may be directed to Project Manager who will assist in support resources needed.
CONTINUED SUPPORT WEEK 12+
  • Unlimited support is received through the professionals at Allscripts Support.

*Scheduling conflicts, building construction, data conversion requirements, and any delay in client responsibilities may result in a delay to the timeline.
**We will only be able to move as fast with the implementation process as you are able to review the classes that will teach you all about MyWay.

 